I-90, Albany, NY



A total of 378 slabs, (some are visible above) were placed on this two mile rehabilitation project on I-90 in Albany, N.Y. in 47 night closures. A value engineering proposal utilizing the Super-Slab® System, initiated by the contractor, resulted in the repairs being made in about half the time when compared to the specified rapid set concrete method. The entire six lane highway was open during the hours of heavy traffic volume—every day..

 

Back

Next


Specialized grading equipment, shown below, was used to provide an accurate subgrade surface. This facilitated rapid slab placement and allowed opening the slabs to traffic before they were grouted, enabling the contractor to use the entire work window for slab replacement work. After all of the repairs were made the pavement was overlayed with asphalt concrete.

Owner
New York State Department of
Transportation, Region 1

Contractor
Fahs Rolston Paving Corporation

Engineer
New York State Department of
Transportation, Region 1