A Model for Accelerated Design-Build Construction

Project Stakeholders

  • Owner: The New York City Department of Transportation
  • Contractor: Granite Halmar Construction Company, Inc.
  • Superstructure Erector: Imperial Ironworks, Inc.
  • Engineer: Gannett Fleming, Inc.

Project Overview

The Belt Parkway Bridge over Ocean Parkway in Brooklyn, NY, was a 45-year-old, two-span structure in need of full replacement. Given its high traffic volume (166,000 vehicles per day) and proximity to hospitals, schools, and businesses, traditional multi-year construction was not an option.

To ensure speed, cost-efficiency, and minimal traffic impact, the New York City Department of Transportation (NYCDOT) selected a design-build construction approach with precast bridge components to accelerate the timeline. The Granite Halmar Construction Company, Inc. (contractor) and Gannett Fleming, Inc. (engineer), in collaboration with Fort Miller Precast, delivered a high-quality bridge in a single construction season, demonstrating the power of design-build innovation.

Recognized as one of the Top 10 Bridge Projects of 2004 by Roads & Bridges Magazine, this project remains a model for high-speed, high-quality bridge replacement in New York City and beyond.

Speed: Single-Season Completion with Precast Efficiency

Using a design-build construction model, the project team cut the construction timeline from 3–4 years to just 256 days, completing the bridge 29 days ahead of schedule.

  • Prefabrication at Scale: 51 precast superstructure units were pre-assembled at Fort Miller’s facility, ensuring a precise fit before arriving on-site for rapid installation.
  • Seamless Construction Phases: The project followed a staged approach with a temporary bridge adjacent to the site, allowing traffic to continue flowing without detours.
  • Minimal On-Site Work: Thanks to modular precast components, labor-intensive on-site assembly was reduced, keeping construction on schedule and under budget.

Traffic Mitigation: Keeping NYC Moving During Construction

Maintaining traffic flow was a top priority in this high-density corridor. The project team eliminated major traffic disruptions while replacing the bridge by adhering to design-build coordination and smart staging of precast sections.

  • No Peak-Hour Lane Closures: Bridge components were installed overnight or during off-peak hours, keeping congestion at a minimum.
  • Efficient Staging Plan:
    • The north half of the bridge was built first while traffic shifted onto the temporary span.
    • Once completed, traffic moved onto the new bridge, allowing the southern half to be demolished and rebuilt.
  • Community Benefits: The accelerated construction timeline saved an estimated $25 million in road user delay costs, benefiting commuters, businesses, and emergency services.

Cost Savings Through Design-Build & Precast Construction

The design-build construction approach, combined with Fort Miller’s precast solutions, delivered significant cost efficiencies and long-term durability:

  • Lower Project Costs:
    • The final project cost was $55.5 million, 8% below the engineer’s estimate.
    • The accelerated schedule minimized labor costs and congestion-related expenses.
  • High-Performance Bridge Elements:
    • Micro silica, fly ash, and corrosion inhibitors extended the bridge’s lifespan.
    • Stainless steel reinforcement was used in the deck, barriers, and parapets, adding just 1% to project costs but doubling the structure’s service life.
  • Faster, More Reliable Assembly:
    • Pre-assembled precast bridge units ensured structural continuity through loop-on-loop closure joints and post-tensioning, eliminating delays.
    • With fewer field adjustments needed, the project maintained its aggressive timeline while ensuring long-term performance.

Fort Miller Precast’s Role in Accelerated Design-Build Construction

Fort Miller’s precision-engineered precast bridge solutions were integral to the project’s speed, quality, and efficiency.

Factory-Controlled Manufacturing ensured the high-strength, 4000 psi concrete met exacting quality standards. Additionally, all 51 bridge units were pre-assembled at Fort Miller’s plant to ensure precision, preventing costly on-site issues. The pre-fabricated bridge segments were then shipped 200 miles and installed in just two weeks per half of the bridge. This limited work-zone exposure improved safety and efficiency.

A Benchmark for Design-Build Infrastructure in NYC

The Belt Parkway Bridge Replacement set a new standard for design-build construction in urban environments, proving that precast solutions and accelerated bridge construction (ABC) techniques can transform aging infrastructure faster, safer, and at a lower cost.

spaanspan installation

Resources & Downloads

Access our product resources and downloads for comprehensive information on our offerings.

Featured Bridge Projects

We have participated in some of the most celebrated bridge projects in recent memory, including the Alexander Hamilton Bridge/Highbridge Interchange, the Kosciuszko Bridge over Newtown Creek in Brooklyn-Queens, New York City, and the replacement of the Tappan Zee Bridge over the lower Hudson River.

Elit Veniam Elit Quis Voluptate Commodo

Excepteur esse exercitation aliquip et. Labore dolore aliqua ullamco consectetur ex. Culpa aliqua deserunt duis sint. Ea nisi anim quis labore eu est consectetur elit aliquip nulla consequat nulla ipsum veniam. Dolor in pariatur eiusmod.